MTX were awarded the contract as specialist turn-key provider and commenced work on site in to design and fit out 10 No. MTX Stone Fruit Ripening Rooms within a brand new 5,500m² building.
The extent of the contract also included the full mechanical and electrical installations for the entire depot which included two chilled water systems; one serving the new production area and the other serving, 10 No. Ripening Rooms, five new cold stores and a dispatch area.
The new purpose built depot features many state of the art advantages to help users with ease of access and energy efficiency. Furthermore all of the temperature controlled areas of the new depot are continuously monitored and controlled via the MTX Ripening Management System (RMS) providing complete control to the client at all times.