Categories: Case Studies

Pratts Bananas Limited – Warehouse Fit Out

MTX were solely responsible for this project from conception to completion, the project brief was to fit-out an existing unit with a new banana ripening facility able to ripen 480 tonnes per cycle with the view for future expansion. The new facility was to include a Holding Area, Packing Area, Quality Control Office, Plant Room and Banana Ripening Rooms.

MTX constructed ten 36 pallet two tier and two 60 pallet three tier ripening rooms all fitted with the unique MTX pallet sealing system along with our reversible airflow ensures uniform ripening. All ripening rooms also fitted with a fan inverter drive, giving us variable airflow and reduced energy consumption.

The cooling media for the site is chilled water, the chilled water system comprises of 3no. 250kW free-cooling chillers controlled from a central sequence control panel, this allowing the client close efficient control of their plant.

Alongside this MTX installed an MTX Plant Visor, which via the internet gives you access to view the status of chilled water plant at any time.

MTX’s in house project teams were responsible for the full design, installation and commissioning package of the mechanical, electrical and refrigeration services. The installation conforms to all current legislations.

The new facility was fully operational within an 18 week programme.

MTX Ripening Technology

Recent Posts

Loblaws – 12 x 42 Pallet Banana Ripening Rooms

Loblaws awarded MTX with the contract to update the ripening rooms at their Boucherville Quebec…

6 years ago

Winfresh UK – Ripening Rooms

Winfresh UK required extra capacity at their Stanstead location, in order to cater for their…

6 years ago

Van-Whole Produce – Banana Ripening Rooms

Van-Whole produce awarded MTX the contract to demolish their existing ten (10) 20-pallet ripening rooms…

6 years ago

Turner’s PPL – Tropical Ripening Rooms

Installation of two, 3-tier random access tropical ripening rooms and a 3-tier blast chiller for…

6 years ago

Save On Foods – 5 x 42 Pallet Banana Ripening Rooms

Save On Foods constructed a distribution facility in Acheson, Alberta. The facility was built by…

6 years ago

Minor Weir and Willis Temperature Controlled Distribution Warehouse

MTX Contracts Ltd successfully completed the design, construction, engineering and commissioning of a new temperature…

6 years ago