The enabling works for the project commenced with work on the 10 No. Ripening Rooms carried out over a strict 15-week programme. In addition to the primary contract works MTX were also contracted to supply and erect an additional office within the existing locker room.
Whilst the Ripening Rooms were installed as per the patented MTX design, the project design team delivered a bespoke design for the vertical baffles on this scheme to achieve increased efficiency from each room. Due to the success of the newly designed silicone rubber baffles, this modification will be carried forward for all MTX Ripening Rooms installed in the future.
The new ripening rooms were successfully completed on programme and within budget and feedback from our client has been excellent.
Loblaws awarded MTX with the contract to update the ripening rooms at their Boucherville Quebec…
Winfresh UK required extra capacity at their Stanstead location, in order to cater for their…
Van-Whole produce awarded MTX the contract to demolish their existing ten (10) 20-pallet ripening rooms…
Installation of two, 3-tier random access tropical ripening rooms and a 3-tier blast chiller for…
Save On Foods constructed a distribution facility in Acheson, Alberta. The facility was built by…
MTX Contracts Ltd successfully completed the design, construction, engineering and commissioning of a new temperature…